The Triangle Café at Napier University was a 3 week contract that consisted of the stripping out and removal of existing steel handrails, flooring and sections of concrete wall and slab. New automatic sliding doors were placed in the entrance with advanced sensors that consisted of built in monitors detecting any errors. All steel work for the handrails were removed and replaced with new glazed railing.
The remainder of the building was fully operational as the high quality specification was delivered on programme with continuity and minimal disruption.
Napier University
Edinburgh
£45k
3 Weeks
August - September 2015