The contract involved the complete strip out and refurbishment of the Language Suite comprising 3No Interpretation Suites, 1No Language Lab, 1No Self Study Facility and upgrading of corridors and associated stairs, to produce state of the art learning facilities with some of the most advanced communication technology in the world. The remainder of the building was fully operational throughout the contract, with all IT and building services being maintained throughout.
The works comprised:
SJS provided added value on this project by producing a full scale mock sample booth in our bespoke manufacturing facility. This allowed the clients staff to simulate the user experience of these complex but critical facilities and therefore accurately determine the key functionality and layout of the booths prior to manufacture ensure a bespoke solution tailored to the exact end user requirements.
Heriot Watt University
Edinburgh
£585k
12 Weeks
June - August 2012