NPV (Edinburgh Ltd) – Caledonian Exchange – Brazilian Consulate Fit Out

This construction project comprises of alterations and refurbishment Cat A & B of the existing level 0 floorplate within Caledonian Exchange Edinburgh

Full works Comprising:

  • Strip out works/demolition including isolation permits, removal of ceilings and floor coverings, removal of retaining walls, slabs and soft ground/Install new retaining walls/slabs
  • Testing and isolating existing M&E services
  • Removing M&E services (luminaires, fire alarm, security, data, vent, power and pipework)
  • Fit new luminaires, power, security, data and fire alarm
  • Fit new mechanical vent, VRF pipework and above ground drainage
  • Install new sanitaryware
  • Construct/install new partitions, plasterboard upstands/curtain walling, infill coffered ceiling
  • Fit new suspended ceiling rafts, door kits, tea preps
  • Fit new manufactured joinery booths/seating/spur shelving
  • Supply and fit new glazed Komfort screens, skirtings, facings to match existing/flooring
  • Decoration/new wall coverings, new tiling
  • M&E Testing and commissioning
Client

NPV (Edinburgh ltd)

Location

Edinburgh

Dates

September 2024

Duration

21 Weeks

Value

Undisclosed

Date

October 1, 2024

Category

Bespoke Joinery, Projects